Enter the planned submission date in the box below to see internal deadlines for proposal processing.
| Proposals steps | Proposal processing timeline | Due date |
|---|---|---|
| 1 | Send initial "Notification of Intent to Submit" (15 business days prior) |
|
| 2 | Send contact information of subcontractors (if applicable) (12 business days prior) |
|
| 3 | Send draft budget and justification for review and finalization (10 business days prior) |
|
| 4 | Complete the Grant Questions in GMS and certify proposal file for review (7 business days prior) |
|
| 5 | Send other final documents required for submission (except final summary and project description) (5 business days prior) |
|
| 6 | Send final summary and/or project description (1 business day prior) |
|
| 7 | Proposal submission (RGC submission date) |